[Civil Appeal Nos.8957-8958 of 2013]. These appeals have been preferred against the impugned judgment and order dated 10.12.2010 passed by the High Court of Gujarat at Ahmedabad in Special Civil Application Nos.5036-5037 of 2010, reversing and setting aside the order dated 12.3.2010, passed by the Addl. District Judge, Fast Track Court, Surat in Misc. Civil Appeal Nos.29 and 30 of 2008 as well as the order dated 28.9.2007, passed in Special Execution Petition Nos.17 and 18 of 2007, passed by the 2nd Additional Senior Civil Judge, Surat. Facts and circumstances giving rise to these appeals are that: A contract for re-construction of cement godown, site office and warehouse for LPG Plant at Kawas in Surat District was awarded by the appellant to the respondent to be completed on or before 8.8.1984 vide agreement dated 9.2.1984. The respondent completed the work with an inordinate delay and possession could be taken by the appellant only on 31.6.1985.
↧